Inside.mines.edu personal sites transition – A. Guerra

10%

Status

In Process [In Process]

10% complete, updated on Wed 5/8/24 11:22 AM by Connie Schamaun

Changed Percent Complete from 0% to 10%.
Changed Health from None - No health has been set to Green - On track.
From Karie: I have contacted the users to let them know about student support. I will be assigning and onboarding students after commencement so many are waiting for more information from me.

Details

Dates
Thu 2/22/24 - Fri 6/7/24
Acct/Dept
Civil and Environmental Engineering
Service
General Help / IT Service Desk
Type
IT-General / Decommision Technology
Health
Green - On track
Created
Sun 4/14/24 1:02 PM
Modified
Wed 5/8/24 11:22 AM

New Project Request

Point of Contact
This can either be the project manager or the person who knows the most about the project. Note that the project manager is assigned after the project is created.
How can we help you?
Please provide details regarding your request? Do you have a solution defined or do you need support identifying a solution?
Could you please transfer the info on my inside.mines page to a secure location. And then also provide instructions as to how I could update this.

Thank you!
Provide the background of this request.
What events or discussions preceded this request? Have there been previous efforts related to this request? Are you working with a vendor already? What are the benefits of this initiative?
Mines is decommissioning inside.mines.edu.
What is the desired completion date?
Please note that projects will be completed based on resource availability and prioritization.
06/07/2024
What are the factors driving the desired completion date?
Are there campus activities, legal requirements, dependent efforts or goals that are driving a date?
Mines is decommissioning inside.mines.edu.
Provide the executive leader(s) who will champion this initiative?
These individuals support the success of this effort, such as removing obstacles, sending strategic communication and promoting necessary policy changes.
Andrew Moore
What team members have been identified to help drive this initiative?
Please note that involvement of department team members is critical to the success of this inititive.
Karie Farr, Connie Schamaun
Any additional information about this request that you would like to include?
Who does this project help? What happens if this project is not completed?
N/A

Description

Could you please transfer the info on my inside.mines page to a secure location. And then also provide instructions as to how I could update this. 

Thank you!

Manager

Alternate Manager(s)

Sponsor