TRAIL Implementation (OreConnect)

55%

Status

In Process [In Process]

55% complete, updated on Fri 5/3/24 3:46 PM by Julie Gabriel Sharpe

Changed Percent Complete from 90% to 55%.

Summary: As of 5/3/2024, the Faculty/Staff Just-in-Time provisioning integration is still not working. Susan and Julie both tried to escalate with ReadyEducation but no forward progress has been made. Robin completed the Accessibility review and the team (Susan, Ciel, Robin, Ethan, Julie) will meet next week to discuss. The Student Data API integration is running nightly, and Susan has reported that future admits (i.e. not yet enrolled at Mines) are being sent to OreConnect. This is an open issue that will need to be addressed. Julie will reach out to project team members to collect lessons learned, and we'll ensure open items are smoothly transitioning and moved into an operational queue as this project closes.

Completed Milestones or Key Activity (in this reporting period): 
Accessibility review – Robin performed the accessibility review. Meeting the week of 5/6 to discuss. 

In Progress/Remaining Key Activity:
Employee Just-in-Time Provisioning: Requested that ReadyEducation do their side of the integration work in late February 2/27. No response until 4/19 at which time the item did not work as expected. It is back in ReadyEducation's queue. (Sisan escalated to her vendor-side contact, Orterio.)
Transition to Operations: Julie will reach out to project team members to collect lessons learned, and we'll ensure open items are smoothly transitioning and moved into an operational queue as this project closes.
Non-production Environment (ADDED in January): Team is exploring how to leverage the available Sandbox environment to develop/test integrations in the future. Right now, it is not ready for that use case.  

Risks/Issues:
- Issue: Mines has been waiting on ReadyEducation to complete their side of the employee just-in-time (JIT) provisioning, which was sent to them in mid-February.  Susan, John and Julie requested a meeting with ReadyEducation for the week of 4/15. As of 4/19, the item was ready for testing but did not work. As of 4/20, the item is back in ReadyEducation's queue. 
- Issue: Non-degree data, as well as future admits, are being sent to OreConnect via the student data integration. (Team needs to determine plan for addressing these types of records in the future.)
- Risk (Downgraded given EMS has been removed): Not having a functioning non-production environment may complicate setup/testing of integrations after the initial go live of OreConnect. (Mitigation: Research feasibility and what is required to use the 'sandbox' as a non-prod. Asked ReadyEducation for input and/or client contact info. Review outcome with John, Susan and team.) 
 
Items that will move to Operational Queue (given need date):
Add OreConnect tile to SSO portal when TRAIL is ready – Susan would like to wait until August (post-Pilot) to add the tile.  
Payment Gateway – Per Susan, this will be needed in production in August 2024. (Julie/Susan/John to discuss when to put in the operational queue given this target date.)

Details

Dates
Fri 7/28/23 - Thu 2/29/24
Acct/Dept
AA Other
Type
IT-General / Systems (implementing a new system)
Health
Green - On track
Portfolio(s)
Created
Thu 8/17/23 3:30 PM
Modified
Fri 5/3/24 3:46 PM

New Project Request

Point of Contact
This can either be the project manager or the person who knows the most about the project. Note that the project manager is assigned after the project is created.
How can we help you?
Please provide details regarding your request? Do you have a solution defined or do you need support identifying a solution?
Susan Gieg - Implementation of Ready Education's Campus Groups, which will be called OreConnect
Provide the background of this request.
What events or discussions preceded this request? Have there been previous efforts related to this request? Are you working with a vendor already? What are the benefits of this initiative?
AA priority
What is the desired completion date?
Please note that projects will be completed based on resource availability and prioritization.
11/17/2023
What are the factors driving the desired completion date?
Are there campus activities, legal requirements, dependent efforts or goals that are driving a date?
Initial soft Launch/Pilot in Fall 2023. Broader launch in Spring - and then again in Fall 2024.
Provide the executive leader(s) who will champion this initiative?
These individuals support the success of this effort, such as removing obstacles, sending strategic communication and promoting necessary policy changes.
Vibhuti Dave
What team members have been identified to help drive this initiative?
Please note that involvement of department team members is critical to the success of this inititive.
Susan Gieg in Undergraduate Studies
In ITS: Primarily John O; Kelly M; Julie S at this time. Some other resources will be assigned.
Any additional information about this request that you would like to include?
Who does this project help? What happens if this project is not completed?
Susan spoke with Dominick about this effort. Assigned to Julie at end of July.