BlasterCard Modernization

35%

Status

In Process [In Process]

35% complete, updated on Fri 5/10/24 4:35 PM by Ivan Cornejo

Changed Percent Complete from 29% to 35%.
Dear All,

Happy Friday!

I wanted to take a moment to provide you with an update on the progress of the BlasterCard project.

I am pleased to report that the status of the project is currently trending positively as indicated by the color GREEN.

This week, I had the opportunity of meeting with the Project Sponsors, namely Andrew Moore, Braelin Pantel, and Noelle Sanchez, for a final review and approval of the Request for Information (RFI) ahead of its scheduled release on Friday, May 17th, 2024.

Following the release, vendors will have the opportunity to review our RFI and submit their written responses by Monday, June 17th, 2024. Upon receipt of these responses, I will be collaborating with the RFI team to meticulously assess the documentation and determine whether any vendors warrant further consideration, including the possibility of providing a demonstration to the team.

Additionally, I am in the process of compiling a comprehensive documentation outlining roles and responsibilities, as well as establishing a schedule for the core RFI team members.

Should you have any questions or comments regarding the aforementioned updates, please do not hesitate to reach out.

Thank you for your attention to this matter.

Warm regards,


Ivan A. Cornejo

Senior Business Analyst, Project Management Office (PMO) 

Information Technology

1600 Jackson Street, Golden, CO 80401

607-368-6953 | ivancornejo@mines.edu 

Uploaded Image (Thumbnail)

Our values: Trust | Integrity | Respect | Responsibility 





 

Details

Dates
Wed 9/6/23 - Thu 8/1/24
Acct/Dept
Information Technology
Type
Software / Hardware / Enhancement (Extending application functionality)
Health
Green - On track
Created
Wed 9/6/23 4:34 PM
Modified
Fri 5/10/24 4:35 PM

New Project Request

Point of Contact
This can either be the project manager or the person who knows the most about the project. Note that the project manager is assigned after the project is created.
How can we help you?
Please provide details regarding your request? Do you have a solution defined or do you need support identifying a solution?
Modernize BlasterCard
Provide the background of this request.
What events or discussions preceded this request? Have there been previous efforts related to this request? Are you working with a vendor already? What are the benefits of this initiative?
There is a strong desire to collect and analyze data to improve student experience and engagement at Mines.
What is the desired completion date?
Please note that projects will be completed based on resource availability and prioritization.
08/01/2025
What are the factors driving the desired completion date?
Are there campus activities, legal requirements, dependent efforts or goals that are driving a date?
Improved customer experience for users.

Student Engagement

Using the BlasterCard application’s ability to improve access services for students, faculty, and staff in conjunction with Lenel (Access Management software).

Expand current BlasterCard offerings to multiple areas on campus.

Reporting

Ability to collect and analyze electronic ticketing for campus events.

Tap functionality for BlasterCard which helps administrators understand who attends events for various programs.

Increase data security for Mines.

Move from On-Prem to a Cloud Solution

Mobile Credential application

Universal payment system for Colorado School of Mines.
Provide the executive leader(s) who will champion this initiative?
These individuals support the success of this effort, such as removing obstacles, sending strategic communication and promoting necessary policy changes.
Andrew Moore
Braelin Pantel
Noelle Sanchez
What team members have been identified to help drive this initiative?
Please note that involvement of department team members is critical to the success of this inititive.
Guy DeLuca
Jackie Twehues
Mary Elliott
Lisa Goberis
Jennifer Phou
Katie Joyce
John Obrecht
Any additional information about this request that you would like to include?
Who does this project help? What happens if this project is not completed?
Not at this time ...

Manager

Sponsor

Stakeholders (16)

Andrew Moore
Andrew Moore
Chief Information Officer
Consulted, Informed
Sponsor
Fri 2/23/24 1:42 PM
Ann Totemeier
Ann Totemeier
IT Project Manager
Consulted, Informed
Informed and Consulted
Fri 2/23/24 3:45 PM
BP
Braelin Pantel
VP Student Life
Consulted, Informed
Sponsor
Fri 2/23/24 1:43 PM
DD
Danielle Davis
Intrm Dir/Contracts/Procurement/Travel
Informed
Informed
Fri 2/23/24 1:47 PM
Dominick Gonzalez Rodriguez
Dominick Gonzalez Rodriguez
Dir Project/Change Management
Consulted, Informed
Informed and consulted.
Fri 2/23/24 1:45 PM
Ethan Crawford
Ethan Crawford
IT Customer Experience Manager
Informed
Informed
Fri 2/23/24 6:13 PM
GD
Guy DeLuca
Structural Trades III
Responsible, Accountable
Responsible and Accountable
Fri 2/23/24 1:46 PM
Ivan Cornejo
Ivan Cornejo
Sr Business Analyst
Responsible, Consulted
Responsible
Fri 2/23/24 3:45 PM
JS
Jason Slowinski
AVP Infra Plan Mgmt/Sustain
Consulted, Informed
Consulted and Informed
Fri 2/23/24 1:44 PM
JP
Jennifer Phou
Bursar
Consulted, Informed
Consulted and informed.
Fri 2/23/24 1:44 PM
JO
John Obrecht
Sr Dir Enterprise Sys/Applicat
Accountable
Accountable
Fri 2/23/24 1:42 PM
KJ
Katie Joyce
Student Life Mgr/Special Projects/Operations
Consulted, Informed
Consulted and Informed
Fri 2/23/24 1:46 PM
LG
Lisa Goberis
Dir SL Business Admin
Responsible, Accountable
Responsible and Accountable
Fri 2/23/24 1:46 PM
ME
Mary Elliott
Executive Director Residence Life & Auxiliary Services
Consulted, Informed
Consulted and Informed
Fri 2/23/24 1:47 PM
Megan Averch-Popp
Megan Averch-Popp
IT Program Analyst
Informed
Informed
Fri 2/23/24 1:48 PM
NS
Noelle Sanchez
Controller
Consulted, Informed
Sponsor
Fri 2/23/24 1:43 PM